If you enter an actual finish date for a task, Project calculates its percent complete to be 100%.
To compare baseline and scheduled dates, on the View tab, in the Data group, click the arrow on Tables, and then select Variance. Baseline dates, however, are not affected by changes that you make to the actual or scheduled dates. Entering an actual start or finish date for a task changes the corresponding scheduled or planned date for that task.